Matched clusters were estimated at 88 move-stations (an even split across a bundled quote line). Jet's Aug 13 drawings show 119 — plus 7 more at A-CE8 / A-S8 never captured in either quote.
Net: roughly +38 stations, +133 hrs. Jet's own SCHEDULED matrix already prices this in — his confirmed Floor 8 sequence runs Sep 14–Oct 1, with Phase 2 running Sep 16–23 as a single window across both sides.
This proposal is built on Haworth's 9th-floor DG1 shipment arriving Oct 2. That delivery is the trigger for both Floor 9 streams — reconfigure and new-station install — and sets the run to a fixed Oct 27 sign-off.
Jet's SCHEDULED matrix has Floor 9 reconfigure running Oct 2–13, with the Oct 12 Thanksgiving gap. The two streams share the window, worked by separate crews.
Adopting Jet's own SCHEDULED dates (Sep 1 audit), Floor 9 reconfigure runs Oct 2–13 — the same crew/window as the new-station install stream, which targets an Oct 2 start too. Previously the plan had these fully sequential (reconfigure finishing before install began); Jet's schedule now has them running concurrently on the same floor for the better part of two weeks.
Reconfigure and install run as separate crews working different zones on Floor 9 during this window — flagged here for crew-assignment coordination, not a scheduling risk.
Phases follow MITG's own quote grouping. Their hours are packed into Jet's own confirmed phase windows above rather than tacked on as separate extension time — see the Floor Map tab for each cluster's specific date.
| Cluster | Phase | Side | Work type | Quote est. | Jet Aug 13 | Delta | Flag | Note |
|---|